

August 2015 – Behind technical room – Area for «biomass storage» and «dry-cooler»

September 2015: Cleaning and preparation works - Area for «biomass storage» and «dry-cooler»

October 2015: Space for silo to store the pellets and biomass boiler

November 2015: Installation of pipings between the
existing and the new technical room

December 2015 – The urban permit for the
planned work awarded

January 2016 - Demo site facilities

February 2016 - Dismantling Curtain Wall A: Main Entrance

February 2016 - Dismantling: Inside works

March 2016 – Retrofitting the façade

March 2016 – Retrofitting inside

March 2016 - Preparing the façade…

April 2016 - Removing windows and frames

April 2016 - Main façade

April 2016 - Replacement of windows: Rear Façade Block N° 6

April 2016 - Replacement of windows:
Façade Block N° 6 in patio

May 2016 - Building of ceilings (Fire Resistant)

May 2016 - Main facade

May 2016 - Replacement of windows:
Façade Block N° 6 in patio

June 2016 - insulation being applied

June 2016 - Further fire-resistant ceilings

July 2016 - Completion of façade windows

September 2016 - Ceiling insulation continues

September 2016 - Roughcasting on the back of façade in block 6

September 2016 - Roof insulation for block 1

September 2016 - Insulation and waterproofing for block 1

September 2016 - Greencom ventilation units

October 2016 - Greencoms Ventilation units

October 2016 - Sensors in Purinovas panels

November 2016 – BRICKER team in front of old and
new façades of the demo site

November 2016 – BRICKER team visiting the old boiler room

November 2016 - Greencom Ventilation gates in the windowsframes

November 2016 - Completion casings in lecture hall 428

December 2016 - Assembly of the cyclone of the biomass boiler

December 2016 - Smoke extractor of the boiler

December 2016 - Handling of silos for pellets storage

February 2017 - Concrete slab supporting the expander vessel for thermal oil

February 2017 - Delivery of 1000L tank for thermal oil

February 2017 - Insulation and plastering for block 1

March 2017 - Expansion vessels for thermal oil

March 2017 - Fibre cement pannels for block 6

March 2017 - Final look of the faade

March 2017 - Piping for moving pellets from truck to silos

March 2017 - Transport system for pellets

April 2017 - wall insulation in courtyard

May 2017 - New heat exchanger between ORC unit and cooling tower

June 2017 - connection for 500kW dry cooler

June 2017 - pressure sensors - biomass boiler

July 2017 - dilatation joint connection between technical rooms