August 2016 – Start of the interventions
at the Turkish demo site

August 2016 - Excavation works at the solar field

August 2016 – Works at the solar field

September 2016 - Window sill
aluminium water drainage detail

September 2016 - Iron works on the solar field

September 2016 - Insulation mock-up works

Adsorption chiller at the factory

Solar field progress

Roof insulation

Early 2017 - installation of electrical cabling trays

Early 2017 - Ultrasonic testing of solar field

February 2017 - AD Chiller Foundation

February 2017 - Design work

Mid-2017 - adsorption chiller installation

Delivery of the adsorption chiller at the demo site

August 2017 - ORC storage foundations

August 2017 - scaffolding on A block's east façade

September 2017 - insulation works on A block's south façade

October 2017 - PTC installation and ORC storage in background

November 2017 - levelling plates for the PTCs

November 2017 - PTC installation

November 2017 - water pipes

December 2017 - construction of piping bridge

December 2017 - first phase of PTCs

December 2017 - pumping equipment