Intervention progress at the Turkish Demo Site

The retrofitting works at the Turkish demo site started in August 2016. The image gallery below shows the works as they progressed. Click here to access the monthly technical progress reports.

  • bricker-cover
    August 2016 – Start of the interventions
    at the Turkish demo site
  • bricker-01
    August 2016 - Excavation works at the solar field
  • bricker-02
    August 2016 – Works at the solar field
  • bricker-cover
    September 2016 - Window sill
    aluminium water drainage detail
  • bricker-cover
    September 2016 - Iron works on the solar field
  • bricker-cover
    September 2016 - Insulation mock-up works
  • bricker-cover
    Adsorption chiller at the factory
  • bricker-cover
    Solar field progress
  • bricker-cover
    Roof insulation
  • bricker-cover
    Early 2017 - installation of electrical cabling trays
  • bricker-cover
    Early 2017 - Ultrasonic testing of solar field
  • bricker-cover
    February 2017 - AD Chiller Foundation
  • bricker-cover
    February 2017 - Design work
  • bricker-cover
    Mid-2017 - adsorption chiller installation
  • bricker-cover
    Delivery of the adsorption chiller at the demo site
  • bricker-cover
    August 2017 - ORC storage foundations
  • bricker-cover
    August 2017 - scaffolding on A block's east façade
  • bricker-cover
    September 2017 - insulation works on A block's south façade
  • bricker-cover
    October 2017 - PTC installation and ORC storage in background
  • bricker-cover
    November 2017 - levelling plates for the PTCs
  • bricker-cover
    November 2017 - PTC installation
  • bricker-cover
    November 2017 - water pipes
  • bricker-cover
    December 2017 - construction of piping bridge
  • bricker-cover
    December 2017 - first phase of PTCs
  • bricker-cover
    December 2017 - pumping equipment